In a special called meeting April 26, Trustees of Joint School District 171 met with Architect Jerry Brotnov of Clarkston, regarding plans for the new classrooms proposed for Timberline Schools.

Initially, trustees had seen floorplans to include four new classrooms to replace the two which were damaged this past winter as well as two more, with enclosed hallways and no stairs, utilizing ADA ramps throughout the new section, and adding ADA accessible restrooms.

Given the short span of time to build before the weather changes, and difficulty in locating or receiving the materials needed, Brotnov advised to do the excavation and foundation work as soon as possible and to build the outside shell of the new addition and two classrooms this year.

The other classrooms could then be added one at a time or both at the same time when prices may not be as high as they are now and the school discovers exactly how much more space is needed.

Trustees approved hiring Brotnov and proceeding with the plans presented. Brotnov indicated he needed two to three weeks to finish the design, have plans approved by the state and put it out to bid.

(0) comments

Welcome to the discussion.

Keep it Clean. Please avoid obscene, vulgar, lewd, racist or sexually-oriented language.
PLEASE TURN OFF YOUR CAPS LOCK.
Don't Threaten. Threats of harming another person will not be tolerated.
Be Truthful. Don't knowingly lie about anyone or anything.
Be Nice. No racism, sexism or any sort of -ism that is degrading to another person.
Be Proactive. Use the 'Report' link on each comment to let us know of abusive posts.
Share with Us. We'd love to hear eyewitness accounts, the history behind an article.